Pipeline Update

The Trans Mtn pipeline is currently installing the pipeline through Camperland.

The route is through the Bridal Falls Waterpark; past the Mini Golf through the overflow parking area; through the dog park and through the upper area of Shady Lane which affects 28 full service sites. It will be the end of April or the beginning of May before they are done.

They are committed to returning the Resort to the same, if not better, state than it was before they started. The rows of cedars separating these sites will not be completed until the fall of 2023.

What this means is that we are somewhat limited in our sites that are available until May, and to ensure that we don’t book sites that are not completed (even though they say they will be done), we are not taking any bookings for these sites until June.

We are somewhat at their mercy, but they have been good in their communication with us. We all hope they finish when they say they will!

We appreciate your patience and understanding.

Camperland